Construction Update – October 2022

Structural Steel is 70% Completed

Storm Shelter Masonry is 75% Completed

Underground Plumbing/Electrical is completed in East Area A and Storm Shelter, and 50% completed in West Area A

Exterior Framing and Sheeting is completed in East Area A and West Area A is 50% framed

Slab is being poured in Multi Purpose Gym, with East Area A following

Roofing and interior framing will begin soon

Exterior brick will begin in November