Structural Steel is 70% Completed
Storm Shelter Masonry is 75% Completed
Underground Plumbing/Electrical is completed in East Area A and Storm Shelter, and 50% completed in West Area A
Exterior Framing and Sheeting is completed in East Area A and West Area A is 50% framed
Slab is being poured in Multi Purpose Gym, with East Area A following
Roofing and interior framing will begin soon
Exterior brick will begin in November